Developers must provide us with 'As Constructed Information' for all new sub-divisions and land development including water and sewer reticulation.

Water Reticulation

Information to be provided includes:

  • Offset from building line to main
  • Where a road crossing occurs, the distance from the fittings (levels) to the nearest property side boundary
  • Where a main changes alignment, the distance from the nearest property side boundary to fittings (bends)
  • Distance from fire plugs and valves to nearest property side boundary

Sewer Reticulation

The following levels to AHD:

  • Manhole entrance and exit inverts
  • Property connection 'top of caps'
  • Top of manhole

The following measurements are to be provided:

  • Distance from property connection to centre of nearest downstream manhole
  • Distance from property connection to nearest property side boundary